March 7, 2011 - Construction activities this week
For the week of March 7 to March 12:
Monday (March 7) - A concrete topping pour with machine trowel finishing will extend into the evening.
Tuesday to Friday (March 8-11) - There will be an increase in personnel at the site for the afternoon shift (3-11pm). However, all work will be inside the building and is not expected to create high noise levels.