ActivityPossible Acoustic Issues
Concrete Formwork
  • Moving / Placing Metal Form panels,
  • Occasional hammering on metal form may occur
  • Placing of wood blockouts in form will require some sawing / nailing.
Reinforcing Steel
  •  Handling of steel bars into position - reasonably quiet
  • Occasional cutting of bars will be required ( power saw )
Concrete Placing & Finishing
  •  Delivery and pumping will be scheduled to be completed before 8:00 PM.
  • Concrete finishing of slabs will be done by power trowel - sound will be similar to a small lawnmower
  • Concrete equipment will likely be removed off-site when work completed- exit will have to be via Skeena
Electrical installations
  •  Workers will be on site but no significant noise anticipated
Plumbing installations
  •  Workers will be on site but no significant noise anticipated
Cranes
  •  Cranes will be working most evenings however they are electric powered and very quiet.