June 28, 2010 - Construction work this week
Monday - concrete formwork and reinforcing.
Tuesday - concrete formwork and reinforcing.
Wednesday - a concrete pour is scheduled for the vertical cores - this work is scheduled to be completed prior to 8:00 PM so there may not be any noise created after 8:00.
Thursday - stat holiday - no construction activity.
Friday - a concrete slab pour is scheduled. There may be some power trowel finishing after 8:00.
Saturday - concrete formwork and reinforcing.