June 21, 2011 - Construction update
For the week of June 20 to June 25:
Evening work will include the continuation of wood cleaning and finishing as well as concrete finishing activities. Both will generate minimal noise.
On Tuesday and Wednesday (June 21 and 22), air handling units are scheduled to be lifted onto the roof. There will be extra trucking and crane equipment on Skeena Road during this operation.
Construction of the access road leading from Parking Lot 3 continues.
On Saturday (June 25), work is scheduled for the interior only, which will generate minimal noise.