Monday- concrete formwork, reinforcing, concrete pour scheduled for vertical cores- completion anticipated to be prior to 8pm
Tuesday- concrete formwork, reinforcing, tilt panel prep, concrete pour for vertical cores- completion anticipated to be prior to 8pm
Wednesday- concrete formwork, reinforcing, tilt panel prep
Thursday- concrete formwork, reinforcing, tilt panel pour and finish
Friday- concrete formwork, reinforcing, formwork stripping
Saturday- concrete formwork, reinforcing, tilt panel pour and finish