July 26, 2010 - Construction work this week
This week, all the concrete panels are being tilted.
Late evening work will be continuation of the formwork and reinforcing steel at cores 2 and 3. Core 1 (farthest west) is complete.
Monday and Thursday are moving days for the big crane which by necessity will require a lot of activity on Skeena Road (during normal hours).
Tuesday and Wednesday will be tilt-up days and will likely have evening activities on formwork.
Thursday evening will be reinforcing steel and formwork.
Friday evening there will be concrete slab power trowel finishing.
Saturday morning there are no noise related activities scheduled before 9 am.