July 21, 2010 - Updated activities this week including those may carry on after 8:00 p.m.
Monday: Concrete pour for walls - expect delivery and placing to be complete by 8 pm. Some finishing after but minimal noise impact.
Tuesday: Reinforcing steel placement - minimal noise impact.
Wednesday: Formwork construction - some noise from the steel form system being worked on.
Thursday: Concrete slab pour with power trowel finishing likely to carry on past 8 pm.
Friday: Concrete pour for walls - expect delivery and placing to be complete by 8 pm. Some finishing after but minimal noise impact.
Saturday: Preparation for concrete pour which will start after 9:00 am. No deliveries before 9 am