July 19, 2010 - On July 27th, 28th and 29th the cement "tilt-up" walls of the film centre will be going up

 

On July 27th, 28th and 29th the cement "tilt-up" walls of the film centre will be going up.  You may like to watch.  Essentially the full enclosure of the sound stage will be erected (these will be 45' high panels).  Also the north and east walls of the theatre will be going up and they are roughly 30' high.  Each panel will take about an hour and a half.   Roughly 1/2 hour to prepare, 15 minutes to pull it up, 1/2 hour to brace and weld it, and then the equipment will be mobilized to start the next panel.