July 12, 2011 - Construction Update

For the week of July 11th to 16th:

There will be a continuation of the timber and concrete finishing program starting mid-week. Both activities will generate minimal noise.

Construction of the new access road continues from Parking Lot #3 to the north side of the film centre.

This week the removal of the protective "bubble" commences, starting at the east end of the building. This activity is scheduled to begin on Wedneday, July 13th.