February 8, 2011 - Construction activities this week
For the week of February 7-12, the following activities might generate noise beyond the normal 8:00pm noise curfew:
Tuesday (Feb 8) and Thursday (Feb 10) - Concrete topping pour with machine trowel finishing which may carry on into the evening.
Update: Thursday's activity is now rescheduled to Friday (Feb 11).